Cauca Valley | Hidroituango Dam and Reservoir
WI_co215.jpg Hong Kong  |  ConstructionThumbnailsCauca Valley | Hidroituango Dam and Reservoir

This 225 m high embankment dam on the Cauca River is part of a hydropower project under construction. Operation should have started in late 2018, but a landslide earlier the same year (right side of the image) blocked the diversion tunnel. As an emergency measure, the water was led through the power house. The dam was completed rapidly, so that the spillway (seen on the left side of the scene) takes all the runoff at the time of the photo, until the start of operation of the power plant.

Created
Tuesday 9 August 2022 by Martin Mergili in South America / Colombia (567 visits)